Mitsubishi delays Kashima No 2 cracker turnaround

30 June 2008 09:25  [Source: ICIS news]

SINGAPORE (ICIS news)--Japan’s Mitsubishi Chemical has delayed the turnaround schedule for its No 2 cracker in Kashima due to delays in the restart of its No 1 cracker at the same site, a source from the company said on Monday.

“Due to the delays in the restart of the No 1 cracker, the company has decided to delay the turnaround schedule for its No 2 cracker,” the source said.

The 603,000 tonne/year No 2 cracker would be shut on 6 July and restarted on 21 August, the source added.

The cracker was initially scheduled to undergo a turnaround from 2 July to 15 August.

Mitsubishi operates three crackers with a combined capacity of about 1.3m tonnes/year.

To discuss issues facing the chemical industry go to ICIS connect


By: Brian Myung
65 6780 4359



AddThis Social Bookmark Button

For the latest chemical news, data and analysis that directly impacts your business sign up for a free trial to ICIS news - the breaking online news service for the global chemical industry.

Get the facts and analysis behind the headlines from our market leading weekly magazine: sign up to a free trial to ICIS Chemical Business.

Printer Friendly