China’s Liaoyang Petrochemical delays refinery maintenance to Q3

27 February 2013 08:42  [Source: ICIS news]

SINGAPORE (ICIS)--China’s Liaoyang Petrochemical, a subsidiary of PetroChina, has postponed the scheduled maintenance of its 9m tonne/year refinery in Liaoning province to the third quarter, a company source said on Wednesday.

The one-month turnaround may start in July or August, against the original schedule of April-May, the source said.

The refinery maintenance will be conducted simultaneously with the planned upgrade for the company’s 200,000 tonne monoethylene glycol (MEG) plant at the site, the source said.

Delivery of required equipment for the MEG plant upgrade was delayed, prompting the change in shutdown schedule for both the plant and the refinery, the source said.


By: Amy Sun
+65 6780 4359



AddThis Social Bookmark Button

For the latest chemical news, data and analysis that directly impacts your business sign up for a free trial to ICIS news - the breaking online news service for the global chemical industry.

Get the facts and analysis behind the headlines from our market leading weekly magazine: sign up to a free trial to ICIS Chemical Business.

Printer Friendly