Marun shuts down Iran MEG on gas disruption

07 July 2008 15:00  [Source: ICIS news]

SINGAPORE (ICIS news)--Iran’s Marun Petrochemical shut down its 400,000 tonne/year monoethylene glycol (MEG) plant two days ago due to gas supply disruptions to its adjoining cracker but plans to restart it by 1 September, a source close to the company said on Monday.

 

“The plant was shut on 5 July and we understood that there was a gas failure at the [production site] at Bandar Imam,” said the source.

The source was unable to say if the cracker and the other adjacent plants were also down.

The MEG plant receives ethylene supplies from a 1.1m tonne/year cracker at the same site.

 

The latest outage is expected to push MEG spot prices higher. According to global chemical intelligence service ICIS pricing, MEG prices had firmed by $10/tonne to end Monday at $1,090-1,100/tonne cost and freight (CFR) China Main Port (CMP).

 

Marun also operates a 300,000 tonne/year high-density polyethylene unit and a 400,000 tonne/year polypropylene facility integrated with the cracker. At the same site is another cracker operated by Amir Kabir Petrochemical.

 

Both Marun and Amir Kabir are affiliates of state-owned National Petrochemical Co.

 

Hong Chou Hui contributed to this article
For more on MEG visit ICIS chemical intelligence

To discuss issues facing the chemicals industry visit ICIS connect

 

ICIS Copyright © Reed Business Information 2009


Author: Salmon Aidan Lee
+65 6780 4359



AddThis Social Bookmark Button

For the latest chemical news, data and analysis that directly impacts your business sign up for a free trial to ICIS news - the breaking online news service for the global chemical industry.

Get the facts and analysis behind the headlines from our market leading weekly magazine: sign up to a free trial to ICIS Chemical Business.

Links posted in this story:

 

Top

© 2009 Reed Business Information Limited. All Rights Reserved.