Commissioning activity at Indian Oil Corp's (IOC) new cracker and derivatives complex at Panipat, India, is progressing well, according to a company source. Operations at the new 857,000 tonnes/year cracker have started.

"Onspec propylene is in the storage tank and ethylene is expected in a day or two," he said.

Among the derivative units, the polypropylene (PP) plant with a total capacity of 600,000 tonnes/year is due to start first and should be up by end of the week. Next in line are the 350,000 tonnes/year swing high-density polyethylene (hdPE)/linear-low density PE (lldPE) and 325,000 tonnes/year monoethylene glycol (MEG) plants. Operations at the two plants are expected to commence from mid-April.

A 300,000 tonnes/year standalone hdPE plant is currently scheduled to start at end-April.

The start up has been quite smooth so far with commissioning of derivative units delayed only by a few weeks. IOC had said in early March that the PP, MEG and swing PE plant would start operations by the end of that month.

TrackBack

TrackBack URL for this entry:
http://www.icis.com/cgi-bin/mt/mt-tb.cgi/135186

Post a comment

(If you haven't left a comment here before, you may need to be approved by the site owner before your comment will appear. Until then, it won't appear on the entry. Thanks for waiting.)

About

This page contains a single entry from the blog posted on April 6, 2010 10:07 AM.

The previous post in this blog was US Optimism Needs To Be Tempered.

The next post in this blog is Muddled Messages Over Yuan Revaluation.

Many more can be found on the main index page or by looking through the archives.

Related Posts with Thumbnails